Tragedy Strikes: Collapse of On Nut-Lat Krabang Elevated Road Construction Project Causing Death and Injuries

Open details of the On Nut-Lat Krabang elevated road construction project of the Thanawan-Napa joint venture worth 1,664 million baht that caused a collapse that caused many deaths and injuries

There was an incident! bridge under construction Lat Krabang area collapsed on workers

Thread back! Construction “Elevate On Nut – Lat Krabang” budget 1.6 billion, work is not progressing

Showcase of the project “Pink Line Electric Train” opens as early as September this year, expected to be the same price as yellow

On July 10, 2023, from the incident of the bridge girder crossing under construction collapse in front of Lotus, Lat Krabang, Bangkok Initially, there were 3 serious injuries and 4 minor injuries.

Recently, the PPTV news team checked the information and found that the On Nut-Lat Krabang Tollway Construction Project There is a civil office Bangkok Is the owner of the project and the contractor is Tarawan Construction Co., Ltd. and Napa Construction Co., Ltd.

Length of On Nut-Lat Krabang Tollway Construction Project which passed the scene of the bridge collapse

Being a contractor in the name of Thanawan-Napa Joint Venture On Nut-Lat Krabang Elevated Highway Construction Project, Lat Krabang District, Bangkok The project value is 1,938.3 million baht, divided into the Bangkok Office (Bangkok Office) 1,664.5 million baht and the work of the Metropolitan Electricity Authority 273.75 million baht.

According to the contract for the project of the Bangkok Office, construction begins on February 23, 2021 until August 11, 2023, for a period of 900 days, but the latest is expected to be completed in December 2024. which if the contractor is unable to complete the work within the time specified in the contract Must pay a fine to the employer about 4.1 million baht per day.

For the nature of construction, it is a reinforced concrete elevated road, 2,200 meters long, 4 lanes, round-trip, built along the central island of Lat Krabang Road, a distance of 3.5 kilometers, starting from the bridge over the Nong Khla Canal near Soi Lat Krabang 9/7 and ending in front of the Office of the DPW. N. Suvarnabhumi Branch Including building a drainage system lighting system traffic aid system

In addition, the contract states that The contractor must control the work carefully. During the work, there must be a full-time representative who is responsible for supervising the work of the contractor. Including the contractor will be liable for any accidents, damages or dangers arising from the work of the contractor. And will be liable for damage from the actions of the employee. or agent of the employer Including third parties in any damage caused by the operation.

Thank you for the photo: Rama 199 Radio Center and the elevated road construction project on On Nut-Lat Krabang Road.

2023-07-10 13:36:29