In Walia, the dam works were 87.5% completed. It remains to install the valves. However, rising waters are now a threat, notes the minister. Work resumed, despite the project being suspended, to prevent water stagnation in the neighborhoods.

Company representative Bab al-Kheir – Wadi Koundi, engineer Doungous Oumar, explains that construction of a two-valve manifold is planned. He raises the difficulties related to anarchist occupations.

As for the anarchist occupations, the Minister believes that they constitute difficulties that prevent the necessary work from being carried out. This administrative problem will be solved very quickly with the 7th arrondissement city hall to avoid delays in the works and so that the rainy season 2023 is not a nightmare for the populations of these wards.