Road investments in 2022. A2, S6, S7, S11, S19 – ZRID decisions, GDDKiA plans [lista]

In 2022, the General Directorate for National Roads and Motorways plans to obtain a road investment decision (ZRID) for 55 sections of national roads with a total length of approximately 660 kilometers. Most of them concern the Mazowieckie, Lubelskie and Pomorskie voivodships.

Receipt of the ZRID decision is a signal to start work. Road engineers explain that road investments are carried out in the traditional system or the design and build system.

The first of them means that GDDKiA first selects a design office in the tender, whose task is to develop the documentation needed to submit an application for a ZRID decision. In addition to the construction design, an executive design is also prepared, and after obtaining the ZRID decision, a contractor for the investment is selected in a separate tender to implement it on the ground.

“In the case of investments carried out in the Design and Build system, after receiving the Program Concept (KP) or Technical-economic-environmental study with KP elements, we announce a tender to select a contractor for both the design and construction of a given investment. The contractor prepares the necessary documentation, submits an application for issuing the ZRID decision, and after receiving it, it starts work “- informed GDDKiA.

The ZRID decision is issued by the voivode competent for the location of the given investment.

WATCH TVN24 ON THE INTERNET ON TVN24 GO >>>

ZRID decision applications

In the first half of 2022, road workers plan to submit applications for a ZRID decision for 27 road sections with a length of approx. 330 km. The plan for the second half of the year provides for submitting applications for 22 sections with a length of approx. 210 km. Taking into account the total number of kilometers of planned road investments, Podlaskie and Pomorskie voivodships are at the fore.

GDDKiA provided the subdivision for individual voivodeships:

Podlaskie voivodeship (eleven sections, approx. 153.7 km long)

– S19 Kuźnica – Sokółka North,

– S19 Krynice – Dobrzyniewo – Białystok West,

– S19 Białystok Księżyno – Białystok Południe (with the DK65 section),

– S19 Białystok Południe – Ploski,

– S19 Haćki – Bielsk Podlaski West (with the section DK66),

– S19 Bielsk Podlaski West – Boćki,

– S19 Boćki – Malewice,

– S19 Malewice – Chlebczyn,

– DK8 Sztabin bypass,

– DK8 bypass of Suchowola.

voiv. Pomeranian Voivodeship (six sections with a length of approx. 94.6 km)

– S7 Żukowo – Gdańsk Południe together with the Żukowo bypass,

– S6, the second road of the Słupsk bypass,

– S6 Bobrowniki – Skórowo,

– S6 Skórowo – Leśnice,

– S6 Leśnice – Bożepole Wielkie,

– S6 Słupsk – Bobrowniki.

Lubelskie Voivodeship (five sections, approx. 69 km long)

– A2 Cicibór at km 624 + 830 – km 640 + 703,

– A2 km 640 + 703 – Dobryń at km 650 + 300,

– A2 Dobryń at km 650 + 300 – km 657 + 137,

– S19 Lubartów North – Lublin Rudnik.

Mazowieckie voivodship (three sections, approx. 49.8 km long)

– A2 Swoboda at km 561 + 440 – km 580 + 190,

– DK61 Pułtusk bypass,

– DK50 bypass of Kołbiela.

Świętokrzyskie voivodeship (five sections, approx. 47.4 km long)

– S74 / DK9 Opatów bypass,

– S74 Przełom / Mniów – Kielce West,

– DK42 bypass of Wąchock,

– DK73 Morawica – Wola Morawicka (2nd stage of the bypass),

– DK74 north connector to the Opatów bypass.

Śląskie Voivodeship (five sections, approx. 37.1 km long)

– S1 Bieruń – Oświęcim together with the Bieruń bypass,

– DK78 Kromołów – Żerkowice,

– DK78 bypass of Pradeł,

– DK78 bypass of Szczekociny and Goleniów,

– DK78 bypass of Kroczyce.

Podkarpackie Province (three sections, approx. 32 km long)

– S19 Miejsce Piastowe – Dukla,

– S19 Iskrzynia – Miejsce Piastowe,

Greater Poland Voivodeship (four sections with a length of approx. 25 km)

– DK12 bypass of Gostyń,

– DK32 bypass of Żodyń,

– DK72 bypass of Grzymiszewo,

– DK32 bypass of Stryków.

West Pomeranian Voivodeship (four sections, approx. 18.4 km long)

– DK20 ring road of Szczecinek,

– DK31 ring road of Gryfino,

– DK13 Kołbaskowo bypass,

– DK13 Siadło Górne – Szczecin West.

Lubuskie Voivodeship (one section, approx. 7.3 km long)

– DK22 bypass of the town of Strzelce Krajeńskie.

Lesser Poland Voivodeship (two sections, approx. 6.5 km)

– S52 Modlniczka – Modlnica,

– DK94 expansion in Olkusz.

Road investments in 2022

In addition, in the first half of 2022, GDDKiA plans to obtain ZRID decisions for 21 road sections with a length of approx. 250 km. The plan for the second half of the year is to obtain a ZRID decision for 34 sections with a length of approx. 410 km. Most of them concern the Mazowieckie, Lubelskie and Pomorskie voivodships.

Mazowieckie voivodship (nine sections, approx. 114.9 km long)

– A2 Swoboda at km 561 + 440 – km 580 + 190,

– A2 km 580 + 190 – Łukowisko at km 598 + 216,

– DK61 Legionowo – Zegrze,

– DK61 Pułtusk bypass,

Lubelskie Voivodeship (eight sections with a length of approx. 98.3 km)

– A2 Łukowisko at km 598 + 216 – km 610 + 722,

– A2 km 610 + 722 – Cicibór at km 624 + 830,

– A2 Cicibór at km 624 + 830 – km 640 + 703,

– A2 km 640 + 703 – Dobryń at km 650 + 300,

– A2 Dobryń at km 650 + 300 – km 657 + 137,

– Chełm bypass S12,

– S19 Lubartów North – Lublin Rudnik,

– DK74 ring road of Dzwola town.

Pomeranian Voivodeship (six sections, approx. 94.7 km long)

– S7 Chwaszczyno – Żukowo,

– S7 Żukowo – Gdańsk Południe (along with the Żukowo bypass),

– S6, the second road of the Słupsk bypass,

– S6 Bobrowniki – Skórowo,

– S6 Skórowo – Leśnice,

– S6 Leśnice – Bożepole Wielkie.

Podlaskie voivodeship (six sections, approx. 85.9 km long)

– S19 Białystok West – Białystok Księżyno,

– S19 Flat – Hacks,

– S19 Kuźnica – Sokółka North,

– S19 Krynice – Dobrzyniewo – Białystok West,

– S19 Białystok Księżyno – Białystok Południe (with the DK65 section),

– S19 Białystok Południe – Ploski.

West Pomeranian Voivodeship (six sections, approx. 74.1 km long)

– S3 Świnoujście – Dargobiedz,

– S3 Dargobiedz – Troszyn,

– S11 Bobolice – Szczecinek,

– DK13 Kołbaskowo bypass,

– DK20 ring road of Szczecinek,

– DK31 ring road of Gryfino.

Śląskie Voivodeship (five sections, approx. 61.2 km long)

– S1 Oświęcim – Dankowice,

– S1 Dankowice – Suchy Potok,

– DK44 bypass of Oświęcim,

– DK78 Siewierz – Poręba – Kromołów,

– DK78 Kromołów – Żerkowice.

Podkarpackie Province (three sections, approx. 30.7 km long)

– S19 Rzeszów South – Babica,

– S19 Miejsce Piastowe – Dukla,

– S19 Iskrzynia – Miejsce Piastowe (turn of 2022 and 2023).

Greater Poland Voivodeship (three sections with a length of approx. 22 km)

– DK12 bypass of Gostyń,

– DK32 bypass of Żodyń,

– DK72 bypass of Grzymiszewo.

Lesser Poland Voivodeship (four sections with a length of approx. 20.7 km)

– S7 Miechów – Szczepanowice,

– DK28 bypass of the town of Zator,

– DK79 bypass of Zabierzów,

– DK75 Brest Connector (second stage).

Świętokrzyskie Voivodeship (one section, approx. 11.8 km long)

– Opatów bypass S74 / DK9.

Lubuskie Voivodeship (one section, approx. 7.3 km long)

– DK22 bypass of the town of Strzelce Krajeńskie.

photo-source">Main photo source: Shutterstock