Flühli / Schachen
New construction of the Chrutacherbrücke and the Rümligbrücke are cheaper than planned
—
For the two road construction projects in Flühli and Schachen, the cantonal council had granted special loans totaling 9.3 million francs. The new construction of the two bridges could be realized at around 2.74 million francs cheaper than planned.
—
In September 2016, the Cantonal Council approved a special loan of 3.9 million francs for the new construction of the Chrutacherbrücke in the municipality of Flühli. The final bill is now available: the total costs amount to CHF 3.14 million. The approved credit is thus undercut by 0.76 million francs. The cost savings are mainly due to project optimization during execution and thus lower construction costs, writes the Lucerne State Chancellery in a press release on Tuesday. The necessary land acquisition was also cheaper than planned. The fee costs for specialists, however, were higher than budgeted, as additional clarifications were required.