Canacol Energy Denies Appeal Supply Contracts Colombia
Canacol Energy production plummeted from over 200 million cubic feet per day to 45 million cubic feet per day amid a severe liquidity crisis.
The conflict stems from November 2025, when Canacol Energy faced an acute liquidity crisis driven by the drop in its natural gas production, which led it to request a business reorganization process in Canada. In May 2026, cornered by the accumulation of contractual penalties, the company asked to rescind several agreements in order to reduce committed delivery volumes and renegotiate prices to make its restructuring viable.
The affected contracts are divided into three key fronts for the Colombian market: supply contracts for residential users, small businesses, and large commercial clients; transport contracts with Promigás for the use of its pipeline system, including a trust agreement that regulates revenue distribution for the transported gas; and operational services with Canaven, a contract through which this firm handles liquefied natural gas transport.
A Canadian judge denied permission to appeal a ruling from the Alberta Court that authorized Canacol Energy to terminate natural gas supply and transport contracts in Colombia, El Tiempo reported. The judge said that insolvency proceedings under the Companies’ Creditors Arrangement Act often force courts to choose the least harmful alternative. Although the judge recognized that some arguments presented by the appealing companies possessed “disputable merit” by addressing a legal provision not thoroughly analyzed previously and which was key in the first instance, he concluded that systemic risk outweighs the legal discussion.
Surtigas, Gases del Caribe, Gases de La Guajira, Cerro Matoso, Gases del Oriente, and Promigás had sought to challenge the ruling, arguing the agreements were exempt financial or derivative contracts, according to El Tiempo. During the process, Surtigas, Gases del Caribe, Gases de La Guajira, Cerro Matoso, and Gases del Oriente alleged that the first-instance judge ignored judicial precedents, erroneously applied the regulations for eligible financial contracts, and made decisions on the Colombian gas market without expert evidence and contrary to the case file.
Promigás presented five exclusive grounds focused on the post-unilateral termination stage, arguing that the judge erred in assuming Canacol Energy would negotiate new, commercially reasonable agreements in good faith while discarding the risk of failing to reach a consensus.
The court adopted a report warning that blocking contract termination would leave Canacol without short-term funds, disrupting gas networks and power generation in Colombia.
According to the document, a paralysis of the company would lead to the interruption of natural gas supply by the appellants, with material consequences for all stakeholders in Canacol Energy, as well as for the reliability of the electrical grid and power generation capacity in Colombia, and the judge indicated that prolonging the litigation with an appeal would only aggravate market uncertainty.

Canacol formally asked the Superintendencia de Sociedades to recognize and validate the Alberta tribunal determinations to cancel or renegotiate 19 supply and transport agreements, in response to Auto No. 2026-01-780331. The company reported a cumulative negative cash flow of US$70.1 million between November 2025 and October 2026, while the Alberta court authorized an emergency DIP financing of up to US$112 million, of which US$82.5 million had been disbursed in cash as of October 24, alongside US$16.4 million in incorporated letters of credit and a projected additional disbursement of US$7.5 million subject to meeting established conditions, with Canacol having allocated US$10 million as cash backing to cover abandonment fund requirements demanded by the Agencia Nacional de Hidrocarburos.
It had already been mentioned before the Alberta Tribunal that the company lacked cash to operate beyond mid-2026 and that the sale process was stalled precisely because buyers conditioned any offer on terminating the contracts with Promigas.
Those bidders made it clear that operations are not viable under current contract terms and prices, seeking to give legal certainty to the cross-border insolvency process under Canadian CCAA law and prevent an imminent liquidation scenario so the firm can be acquired by a potential buyer or investor.

Industrial clients reported severe impacts from the supply shortfall. Cerro Matoso holds an active contract through 2029 for 16,000 MBTU daily, but actual daily shipments fell to about 300 MBTU in November, forcing the ferronickel producer to stop one production line, operate at 50% capacity, impact 600 employees, and incur losses calculated at $1,500 million per day, while lacking direct conversations with Canacol as contacts are handled via lawyers and asking for authorities to intervene, according to Elheraldo.
Colombia’s natural gas market is critical for its energy grid, with power generation heavily reliant on domestic supply. The market’s vulnerability was exposed when Alberta courts allowed Canacol to terminate contracts, prompting Surtigas, Gases del Caribe, Gases de La Guajira, Cerro Matoso, and Gases del Oriente to argue the agreements were exempt from termination, citing their role in maintaining Colombia’s energy stability.
The contracts, spanning residential, commercial, and transport sectors, highlight the market’s interdependence on a single supplier, whose collapse threatened the reliability of the national grid and power generation capacity.
“The contract contemplated 16,000 MBTU daily, but deliveries dropped first to 11,000 and for November they were located near 300 MBTU daily,” said Ricardo Gaviria, president of Cerro Matoso, adding that the ferronickel producer had to stop one production line and operate at 50% capacity.