ZiG2 Billion Allocated to Gwayi-Shangani Project to Boost Matabeleland North and Bulawayo Infrastructure
Finance Minister Prof Mthuli Ncube allocated ZiG2 billion to the Gwayi-Shangani Water Supply Project in the 2027 National Budget presented on Thursday.
The allocation anchors a ZiG4.3 billion provision for dam construction and complementary infrastructure, including the pipeline and treatment plant needed to deliver water to Matabeleland North and Bulawayo. Prof Ncube said the dam wall has reached 61 metres of its planned 72 metres, placing overall completion at 83 percent.
“Additionally, civil works on the 10MW power plant are now at 80 percent completion,” said Prof Ncube, Finance Minister. “Based on the progress so far and consistent support being provided, works on the dam wall, pump station and power plant are now expected to be fully completed during 2027.”
Transport infrastructure received a ZiG9 billion commitment under the Road Development Programme.
Priority projects include rehabilitation of the Beitbridge-Bulawayo-Victoria Falls Highway and construction of the Kwekwe-Nkayi-Lupane Road, Prof Ncube said.
Government also intends to revive the Bulawayo-Victoria Falls railway line. The National Railways of Zimbabwe is expected to mobilise resources for sleeper and ballast installation and rail replacement to remove operational cautions on the network.
“Key interventions under this programme include installation of sleepers and ballast, as well as some rails that should effectively remove the cautions from the network,” Prof Ncube said.
Bulawayo is slated to benefit from the Provincial Special Economic Zones programme launched to revitalise industrial activity in de-industrialising regions. Prof Ncube said Government will prioritise enabling infrastructure, serviced industrial sites, reliable utilities and streamlined regulatory processes to attract productive investment.