Hume Family Sues Tallgrass Over CO2 Pipeline, Odors
Brady and Kari Hume live 951 feet from a compressor station that began running carbon dioxide through a repurposed pipeline last year, and they say the odors and vibrations have driven them to court and depleted their children’s college savings.
- The Humes sued Tallgrass Energy in Logan County District Court, alleging CO2 transport began in September 2025 without a valid easement.
- Logan County commissioners imposed a six-month moratorium on carbon-sequestration permits on Oct. 6, 2026.
- Colorado health officials advised the family to shelter indoors when odors are present.
- The Trailblazer Pipeline conversion is part of a 392-mile regional project announced in May 2022.
Easement dispute centers on 1981 agreement
The Trailblazer Pipeline crosses the Hume property under a 1981 right-of-way granted for natural gas transport. Brady Hume told county commissioners the easement “allowed for transportation of gas only,” thefencepost.com reported.
In January 2022, Trailblazer secured a new easement from neighboring landowners that added CO2 rights, but no such agreement was ever signed with the Humes, according to the Sterling Journal-Advocate. The Humes’ lawsuit alleges Tallgrass has been moving CO2 across their land without authorization since at least September 2025, the Journal-Advocate reported.

Compressor station built without permits
A substantially larger compressor station was constructed on the Rockies Express natural gas pipeline in 2024 as part of the same project that repurposed the adjacent Trailblazer line for CO2, thefencepost.com reported. Kari Hume said the station was built “following no stakeholder comment period the Humes were aware of” and that it lacked a local building permit and the public notice a project of that size would typically require, thefencepost.com reported.
The original compressor across the road was “about the size of a Tuff Shed,” Brady Hume testified before commissioners, thefencepost.com reported. Logan County approved a 2.07-acre subdivision exemption in January 2024 for “the expansion of an existing natural gas compressor station,” and the new station was built from April through September, thefencepost.com reported.
Family reports health effects from CO2 odors
The Colorado Department of Public Health and Environment advised the couple and their seven children to stay inside if odors are present, thefencepost.com reported. Kari Hume told the Sun Telegraph that CO2 began flowing on Sept. 30, 2025, and within weeks she heard alarms at the station for four days without company contact.
She described a “gloom of stink” that caused her septum to swell, coughing and postnasal drip that took ten days to subside after less than a minute of exposure, the Sun Telegraph reported.
The Humes say the compressor station has been shut off since they filed their lawsuit, after running for more than 150 days the previous year, the Sterling Journal-Advocate reported. Food & Water Watch, citing Oil & Gas Watch, reported the station was projected to release up to 12,600 pounds of hazardous air pollutants annually, Hoodline reported.
Tallgrass defends safety record
Tallgrass has defended its operations, saying safety is its highest priority and that the safety record and operating data associated with CO2 pipeline infrastructure demonstrate these systems can be operated safely and reliably, a statement the company previously provided to News Channel Nebraska, thefencepost.com reported.
County pauses permits as regional projects stall
Logan County commissioners enacted a temporary six-month moratorium on permits for carbon sequestration facilities — including wells, pipelines proposed for conversion to CO2 transport, and associated equipment — on Oct. 6, 2026, the Sterling Journal-Advocate reported.
The move reflects broader regional friction: Summit Carbon Solutions’ multi-state pipeline plan has been delayed by court challenges over eminent domain, South Dakota has banned eminent domain for CO2 pipelines, and a North Dakota judge revoked Summit’s underground storage permit, Inside Climate News reported.
The Trailblazer Conversion Project, announced in May 2022, aims to convert 392 miles of existing pipeline to carry CO2 captured from ethanol plants, a Congressional Research Service snippet noted.
Family presses on after selling second property
The Humes sold a second property and cashed in their children’s college accounts to fund the litigation, Hoodline reported. “We could feel it in our bedroom at night,” Brady Hume told commissioners, thefencepost.com reported. With the moratorium in place and their lawsuit active, the dispute over what their easement allows remains unresolved.