Data Center Construction Costs Jump 13% in 2026, Turner & Townsend Says
Data center construction costs jumped 13% in 2026, driven by intense demand for artificial intelligence infrastructure that far outpaced the supply of powered land and skilled labor.
This increase represents roughly three times the ten-year average, according to a report from the global project management firm Turner & Townsend.
The market faces a fundamental disconnect between the aggressive delivery schedules required by tech developers and the logistical capacity of the construction sector. While global inflationary pressures showed signs of stabilization this year, the localized surge in specialized labor and equipment requirements kept upward pressure on project budgets.
Contractors Bake Risk into Pricing
Developers are paying a premium for speed as contractors add large risk allowances to handle compressed timelines. These costs often manifest as mandatory overtime, higher fees for accelerated delivery, and increased labor attraction allowances.
“More aggressive schedules tie to contractors in particular and subcontractors baking in more risk allowances in their pricing. So whether that’s acceleration allowances, whether that’s more overtime and labor attraction allowances, even just higher fees for taking on the risk of delivering at a faster pace than what they would traditionally take on.”
That analysis came from Paul Barry, North America data center lead for Turner & Townsend, as reported by CNBC. Barry said that these factors, combined with ongoing supply chain strains, have created a uniquely challenging environment for capital expenditure management.

Regional Variations in Power Costs
Securing utility connections remains a primary bottleneck for development, with 56% of industry experts surveyed by Turner & Townsend identifying power as a major obstacle. The time required for these connections frequently spans one to two years, while nearly a third of respondents reported waits exceeding two years.
| Region | Cost per Watt (60MW Design) |
|---|---|
| Silicon Valley | $15.01 |
| Dallas | $10.51 |
The sector's financial scale is expected to grow substantially over the coming decades. According to a report from PwC, global capital expenditure on data centers is projected to climb from approximately $800 billion this year to $1.8 trillion annually by 2050. The United States is positioned to capture nearly half of this global investment in artificial intelligence infrastructure, including both chip manufacturing facilities and data centers.
Labor Constraints and Future Outlook
Contractor capacity remains thin, with only about 25% of survey respondents indicating they have sufficient resources to manage current construction backlogs. The shortage of labor and specialized management expertise remains a major obstacle for developers trying to scale operations.
Looking toward the next fiscal year, Barry anticipates a slight moderation in cost escalation, with projections for increases settling into the 6% to 10% range. Many major projects are already underway or have recently entered the procurement phase, meaning that current cost risks are largely locked into existing contracts.
Whether this rate of project starts remains sustainable depends on continued capital flow into the sector. As organizations attempt to navigate these rising costs and supply chain complexities, they are increasingly relying on specialized project management consultants and construction law firms to mitigate risk and ensure compliance with complex utility and labor regulations.
The industry must now determine if the current surge in 2026 represents a peak in project procurement or the beginning of a sustained, long-term trajectory. It remains unclear how long the current labor supply shortage will persist or how quickly utility providers can scale their infrastructure to meet the projected $1.8 trillion demand by 2050.
Turner & Townsend traces its roots to a quantity surveying partnership founded in Darlington in 1946. It expanded internationally with its first overseas office in Johannesburg in 1982 and later managed the construction of The Shard, London’s tallest building upon completion.
The firm was restructured as a limited liability partnership and, in 2021, CBRE Group acquired a 60 percent stake for £960 million, raising its share to 70 percent after merging its own project management arm in January 2025.
“If this demand continues, then there’ll be more continued flow of project starts and so on, but I think we’ve hit a big surge in 2026, especially of new big major projects that have been procured,” said Barry.