Tepco Advances Fukushima Unit 2 Fuel Removal Using Remote Equipment
One hundred twenty-six nuclear fuel assemblies have been safely removed from the storage pool at the No. 2 reactor building of the Fukushima No. 1 nuclear power station, Tokyo Electric Power Company Holdings announced.
The fuel removal operation began in June using remote-controlled equipment, according to The Japan Times. The power station in Fukushima Prefecture suffered heavy damage during the March 2011 major earthquake and tsunami and remains under decommissioning.
Unlike the No. 1 and No. 3 units, the No. 2 reactor did not experience a hydrogen explosion. The building housing the reactor avoided major structural damage, though radiation levels around the spent fuel pool remain high.
Workers created an opening in the wall of the reactor building to facilitate the extraction. Specialized remote-controlled equipment utilizing three cranes places fuel assemblies removed from the pool into a container called a cask, which is then extracted through the wall opening.
Workers from a company cooperating with the plant decommissioning load the fuel into the casks. They practiced beforehand using mock fuel assemblies nearly identical to real assemblies in shape and weight.
“We have been able to carry out the work safely by drawing on our experience.”
said a worker who is from a company cooperating with the plant decommissioning and responsible for loading the fuel into the casks, when speaking to reporters.
Tepco adjusts the length of the crane arms by a few millimeters. A power supplier official said that removing each fuel assembly takes less than an hour.
“We want to complete the mission by communicating with each other closely and steadily carrying out each task.”
said an official of the power supplier.
The removal work has been suspended since Oct. 19 for equipment inspections. Operations also paused to secure sufficient space in the plant’s common storage pool, where the removed fuel is transferred.
Out of 615 total fuel assemblies in the pool, including unused ones, 126 have been removed so far. Tepco plans to resume the operation around spring next year, aiming to complete the work by the end of fiscal 2028.