Maryland Restarts American Legion Bridge Replacement With Scaled-Back Plan

Maryland Restarts American Legion Bridge Replacement With Scaled-Back Plan

November 19, 2026 Newsroom News

Maryland has reopened the path to replacing the 64-year-old American Legion Bridge, releasing a pre-solicitation memorandum this week that invites private companies to propose financing and construction options for a scaled-back project along the Capital Beltway and I-270.

More than 230,000 vehicles cross the bridge daily.

The Maryland Department of Transportation document outlines a plan covering roughly 6.5 miles: from the bridge along the Capital Beltway to the I-270 west spur, then north along the spur. It restarts a conversation that stalled in 2023, when Gov. Wes Moore’s administration questioned whether the original agreement delivered sufficient value to Maryland taxpayers.

No financing or construction method has been chosen. Public funding remains on the table alongside a public-private partnership, and state officials stress that no decision has been made on how the work would be delivered.

The stakes are practical ones for commuters between Montgomery County, Maryland, and Fairfax County, Virginia, where the bridge carries the Capital Beltway over the Potomac River. State officials estimate the corridor endures about 12 hours of congestion daily, and the state recorded 1,000 crashes along the proposed widening stretch over three years, a third involving injury or fatality.

American legion bridge june
Photo: marylandmatters.org

Traffic exceeds bridge capacity

The bridge opened in 1962 as the Cabin John Bridge with six lanes, was renamed in 1969, and was expanded to 10 lanes in 1992. Daily traffic has grown from roughly 48,000 vehicles in the 1960s to more than 230,000 today.

State Highway Administrator Will Pines called it “the worst bottleneck in the state for freight mobility,” telling Maryland Matters that “all those Amazon trucks and the packages that people get every day are greatly impacted for this interstate corridor.” The bridge, built in 1962, is considered at or near the end of its useful life.

American Legion Bridge replacement could cost billions. What's the plan? — ABC 7 News – WJLA

What the new proposal includes

According to the transportation department’s memorandum, the concept would:

  • Replace the American Legion Bridge.
  • Add two high-occupancy toll lanes in each direction along about four miles of I-495, from the Virginia express lanes to the I-270 west spur.
  • Convert existing high-occupancy vehicle lanes and add managed lanes along roughly two miles of the I-270 west spur.
  • Improve connections and transportation options along the corridor.

Transportation Secretary Katie Thomson said in a statement that Maryland has “demonstrated our commitment to advancing delivery of a new American Legion Bridge that supports the current and future needs of the corridor,” adding the project would support “new transit and bike, walking and rolling access across the Potomac River.” The statement frames the project as a congestion and multimodal effort.

How the 2023 deal fell apart

The current proposal is a narrower version of a plan first advanced in 2017 under then-Larry Hogan: an estimated $7.6 billion project to add express toll lanes along portions of I-495 and I-270, with an Australian company, Transurban, financing, building and operating the lanes and collecting tolls from drivers who used them.

Maryland Restarts American Legion Bridge Replacement With Scaled-Back Plan
Photo: capitalgazette.com

That arrangement collapsed in 2023. The Moore administration questioned whether it provided sufficient value to taxpayers, environmental litigation added uncertainty, and Transurban withdrew. The new concept would still include managed toll lanes, but the state is weighing different ways to finance and deliver the work.

Maryland Matters, which obtained the internal memo, noted officials acknowledged the fastest and most likely path would be partnering with a consortium that builds and profits from the project — while cautioning that no decision “to deliver the project as a P3 or proceed with any solicitation” has been made.

Federal money and a $60 million down payment

Maryland has requested $864 million through the federal Bridge Infrastructure program to help improve eight spans on Interstate 495, including the American Legion Bridge. Thomson called the grant “an important down payment,” saying it would cover costs such as right-of-way acquisition that would not be recoverable under a partnership.

Instagram

The state currently has about $60 million programmed for early work. Pines told Maryland Matters he believes the trimmed project would cost less than the original $7.6 billion, even with recent construction cost increases — but “it’s definitely in the billions,” and updated estimates await current market conditions.

Local officials push for more than roads

Adam Van Grack told WJLA the region needs more than highway widening.

“It’s not just about fixing the pathways and the roads, we’ve got to emphasize public transportation significantly better. We’ve got to make sure we give Metro the support needed, but at the same time we’ve got to do something better with our roadways. And if we are not gonna go the route of a second crossing of the Potomac River, which seems to be the way we are going, we’ve gotta do a better job with the American Legion Bridge.”

The project does not include a second Potomac crossing.

Where the timeline stands

Officials plan to meet interested private companies in December 2026 and January 2027. Under the draft memo Maryland Matters obtained, applications for partnership concepts could follow in early 2027, the Board of Public Works could be asked to designate the project a partnership in mid-to-late 2027, and a final agreement could close by early 2029.

The department issuing the memorandum traces its modern structure to 1971, when the state consolidated its transportation functions under a single department led by a cabinet-level secretary — the first of whom, Harry R. Hughes, later became governor. Today the Maryland Department of Transportation comprises five business units and one authority, spanning highways, transit, the port, aviation and motor vehicles, with its own police forces under the transit authority.

The Transportation Secretary also serves as chairman of the Maryland Transportation Authority, the entity that would weigh any toll-backed partnership for the bridge. The department’s current secretary, Katie Thomson, took office in 2025, the same year the state began rethinking how the replacement should be delivered.

Between now and then, congestion on a bridge carrying four times the traffic it opened with will not wait. Construction, whichever path the state chooses, remains years away.

Share this:

  • Share on Facebook (Opens in new window) Facebook
  • Share on X (Opens in new window) X

More on this

  • MoDOT KC Opens Public Comment on U.S. 40 Safety Plan Dec. 10
  • Mark Ivanir Plays a Cult Leader Whose Chosen Disciple Walks Away

Related

Search:

World Today News

World Today News is your trusted source for global journalism — breaking headlines, in-depth analysis, and reporting from around the world.

Quick Links

  • Privacy Policy
  • About Us
  • Accessibility statement
  • California Privacy Notice (CCPA/CPRA)
  • Contact
  • Cookie Policy
  • Disclaimer
  • DMCA Policy
  • Do not sell my info
  • EDITORIAL TEAM
  • Terms & Conditions

Browse by Location

  • GB
  • NZ
  • US

Connect With Us

© 2026 World Today News. All rights reserved. Your trusted global news source directory.
For contact, advertising, copyright, issues email: [email protected]

Privacy Policy Terms of Service