Major Construction and TTC Service Changes on King Street West Through 2027
“Construction will be completed in phases to help minimize disruptions while critical watermain and streetcar infrastructure is renewed,” officials noted in a news release, as Toronto begins a series of major road projects along King Street West that will last through 2027.
The City of Toronto and the TTC have launched a multi-year effort to replace aging watermains and upgrade streetcar tracks.
The work requires lane reductions and intersection closures, forcing significant changes to transit routes. As of November 23, construction is underway between Dufferin Street and Close Avenue, a project expected to continue until fall 2027. During watermain replacement, the city intends to keep one lane of traffic open in each direction, though streetcar track renewal will limit flow to a single lane in one direction.
| Construction Section | Timeline |
|---|---|
| Dufferin Street to Close Avenue | Nov. 23, 2026 – Fall 2027 |
| Spadina Avenue to Portland Street | Dec. 2026 – Summer 2027 |
| Bathurst Street to Shaw Street | Spring 2027 – Late 2027 |
| King Street West and York Street | Summer 2027 |
| Charlotte Street to University Avenue | Fall 2027 – Winter 2027 |
TTC riders have already faced service adjustments, with 504 King streetcars consolidated into a single branch between Dundas West and Broadview stations since November 1. Replacement buses for the 504C and 304C routes are currently running between Roncesvalles Avenue and the Distillery District. The 503 Kingston Road replacement buses have been extended to Dufferin Gate Loop, while 508 Lake Shore streetcar service is suspended.
King Street West originated as the westward extension of the original 1793 town of York plan, reaching its present terminus at Roncesvalles Avenue and Queen Street by 1901 after successive extensions to Peter Street in 1798 and Garrison Creek in 1837.
The corridor now anchors the city’s busiest streetcar routes, 504A and 504B King, which carried an average of 65,000 passengers daily as of October 2018 and connect Lines 1 and 2 at St. Andrew, King, Dundas West and Broadview stations. The section between Bathurst Street and Jarvis Street operates as a permanent transit mall since April 16, 2019, restricting through traffic to prioritize streetcar movement across the downtown core.

Starting in December, 504 and 304 streetcars will divert east via Queen Street West between Spadina Avenue and Roncesvalles Avenue to accommodate work in the Spadina to Portland section. The city plans to manage the impact through traffic signal adjustments, signage, and ongoing monitoring. Access to adjacent businesses, side streets, and pedestrian routes will remain open throughout the construction zones.