Boulder Highway Pavement Improvement Project Begins in Henderson
Table of Contents
Henderson, Nevada – The nevada Department of Transportation (NDOT) commenced a $6.5 million pavement improvement project on Boulder Highway (State Route 205) today, October 26, 2023. The work focuses on a nearly three-mile stretch between Las Vegas Boulevard and Annie Oakley Drive, aiming to enhance safety and prolong the roadway’s lifespan.
The project involves milling and repaving the existing asphalt surface, addressing cracks and other deterioration. this will create a smoother, safer driving experience for the approximately 40,000 vehicles that travel this section of boulder Highway daily. This project is a vital investment in our transportation infrastructure,
stated a representative from NDOT.
Project Details & Timeline
Construction will primarily take place during nighttime hours to minimize disruption to traffic. Motorists should expect lane restrictions between 7 p.m. and 6 a.m. sundays through Thursdays. The project is expected to be completed by late January 2024.
| Phase | Start Date | End Date (Est.) | Impact |
|---|---|---|---|
| Milling | October 26, 2023 | November 15, 2023 | lane restrictions (nighttime) |
| Paving | November 16, 2023 | January 26, 2024 | lane restrictions (nighttime) |
| Striping & Signage | january 27, 2024 | January 31, 2024 | Possible brief daytime closures |
Did You Know?
Boulder Highway, originally constructed in 1931, was one of the first major roadways connecting Las Vegas to Boulder City and the construction site of the Hoover Dam. History.com
Safety Enhancements & Long-Term Benefits
Beyond improved ride quality, the pavement rehabilitation will address safety concerns related to deteriorated road surfaces. Cracks and potholes can contribute to vehicle instability and increase the risk of accidents.The new pavement will also reduce the need for more frequent, disruptive repairs in the future, saving taxpayer dollars.
pro Tip: Check the NDOT website or the Nevada 511 app for real-time traffic updates and road closures before traveling on Boulder highway during the construction period.
“NDOT is committed to providing a safe and reliable transportation system for all Nevadans,” said a spokesperson for the department. “This project is a key component of that commitment.”
The project is funded through state and federal sources. NDOT encourages motorists to drive cautiously through the work zone and be aware of flaggers and construction personnel.
This pavement improvement is part of NDOT’s ongoing efforts to maintain and upgrade Nevada’s highway network.similar projects are planned throughout the state in the coming months, focusing on critical infrastructure repairs and enhancements.
Boulder Highway: A Past and Economic Artery
Boulder Highway has served as a crucial transportation corridor for Southern Nevada for over ninety years. Originally built to support the construction of the Hoover Dam, it quickly became a vital link for commerce and tourism. Today, it remains a major thoroughfare, connecting Henderson and las Vegas, and serving a diverse range of businesses and residents. The ongoing investment in its infrastructure reflects its continued importance to the region’s economic vitality.
Frequently Asked Questions about the Boulder Highway Project
- What is the purpose of the Boulder Highway project? the project aims to improve the safety and longevity