FHWA Lifts Pause on $9B I-45 Project After Signing Agreement With TxDOT; Virtual Meeting Set for Dec. 10
The Federal Highway Administration lifted its pause on the $9 billion I‑45 project rerouting I‑45 parallel to I‑10 north of downtown and to US 59/I‑69 on the east side.
The Federal Highway Administration lifted its pause on the $9 billion I‑45 North Houston Highway Improvement Project after signing a Voluntary Resolution Agreement with TxDOT on Aug. 23, allowing design and construction to resume under federal oversight.
The agreement resolves a Title VI civil rights investigation and commits TxDOT to enforceable timelines for community engagement, affordable housing, flood mitigation and right‑of‑way acquisition, FHWA reported. The NEPA review concluded with no findings. “We have lifted the pause, and with FHWA oversight, TXDOT may proceed with design and construction,” Federal Highway Administrator Shailen Bhatt said.
The session will be conducted in English with Spanish interpretation; free translation, interpretation or disability accommodations are available by contacting public engagement coordinator Gabriel Adame at 713‑802‑5199 no later than 4 p.m. Friday, Dec. 4.
NHHIP Reconstructs I-45 North with Managed Lanes and Flood Mitigation
The NHHIP will reconstruct I‑45 North between downtown Houston and the North Sam Houston Tollway to meet federal safety standards and add four non‑tolled managed lanes, bicycle and pedestrian features, trails along bayous, detention ponds and pump stations for flood mitigation, FHWA said.
The plan also reroutes I‑45 parallel to I‑10 north of downtown and to US 59/I‑69 on the east side, and realigns sections of I‑10 and I‑69 downtown.
TxDOT Executive Director Marc Williams said the corridor, built in the 1950s and 1960s, has not kept pace with a population that has doubled. “The reconstruction of I‑45 will address mobility needs for people and freight, while also improving safety and a number of environmental mitigations that include critical measures to improve storm water drainage,” Williams said.
Community commitments
The VRA requires twice‑annual public meetings through design and construction, displacement and relocation mitigation, drainage improvements, parks and trail connections, highway footprint reductions, structural caps, air‑quality measures and meaningful access for limited‑English‑proficiency populations, FHWA listed. These actions supplement mitigations already in the Record of Decision.
TxDOT recently executed separate agreements with Houston Mayor Sylvester Turner and Harris County. Friday, Dec. 4, 2026. Friday, Dec. 4.