Dún Laoghaire-Rathdown Council Spends €1.2m on Social Housing Before Rebuild
A social housing project in Dublin 18 cost Dún Laoghaire–Rathdown County Council more than €1.2 million before a second builder finished the 13 homes, after the original contractor was fired for missing deadlines and the half-built site deteriorated, The Journal reported.
Documents released under Freedom of Information show the council paid the first developer €984,341 before terminating the contract in August 2022, The Journal reported. Work had started in April 2021 on seven two-bedroom and six three-bedroom houses with a February 2022 completion target. By March 2022 the council wrote to the contractor citing a sick foreman, labour shortages and unreliable sub-contractors as reasons for the stall.
Site left vacant for months
The partially built development sat empty for over eight months while consultant engineers assessed the damage. They found timber frames and insulation in one block had been “exposed to the elements over the past few months” and drainage pipes in the other had degraded in sunlight, The Journal reported. Exposed trenches, waste material and “unsuitable material” created urgent health and safety risks.
Emergency costs climb
An emergency contractor was hired in October 2022 for an initial €142,988. That figure rose to €195,652 in March 2023 and to €229,702 by July 2023 as further defects emerged, The Journal reported. The combined outlay on the incomplete project exceeded €1.2 million before the main rebuild began.
Department flags high per-unit cost
In March 2024 the council sought a revised budget of over €6.3 million — about €486,143 per unit — from the Department of Housing. The department “considered high” the per-unit figure but accepted the costs were not “unreasonable” given the emergency works and the need to finish the homes, The Journal reported.
Final bill still unknown
The second contractor handed over the completed development in September this year. A council spokesperson told The Journal all payments were “made in accordance with the contract”.
| Stage | Cost | Date |
|---|---|---|
| Paid to original contractor | €984,341 | Before August 2022 |
| Emergency works (initial) | €142,988 | October 2022 |
| Emergency works (revised) | €195,652 | March 2023 |
| Emergency works (final) | €229,702 | July 2023 |
| Revised full project budget sought | Over €6.3 million | March 2024 |
The FOI request was filed by a local resident, identified only as Liam, after construction appeared to stall near his home, The Journal reported.
Related reading
- Malaysian Film Wins Special Mention at Oscar-Qualifying Bengaluru Festival
- Czech TV Premieres Krakonoš a Básník Christmas Eve; Four Broadcasters Release Holiday Schedules Through Dec. 26
- What Trump's Housing Order Means for a $360,000 Loan at 7.32% (daybreakwire.com)
- California Announces New Homekey+ Projects and Funding to Address Homelessness and Veteran Housing (newsdirectory3.com)