Arizona Lawmakers Urge Army Corps to Prioritize Flagstaff Flood Project
Two people died in extreme rainfall that hit Flagstaff earlier this month, and the loss of life has sharpened pressure on Washington to move faster on a flood-control plan that has lingered for a quarter-century.
The Rio de Flag Flood Control Project is designed to protect roughly 1,500 structures in the city’s Southside neighborhood, KJZZ reported. The project aims to prevent damage by redirecting the Rio de Flag watershed.
Sens. Mark Kelly and Ruben Gallego joined Representatives Greg Stanton and Elijah Crane in a letter urging the U.S. Army Corps of Engineers to prioritize the safety improvements without further setbacks, according to wisevoter.com. The lawmakers called the infrastructure improvements “an immediate public safety necessity” and pressed the Corps to meet its planned March 2027 deadline for awarding the construction contract. Flagstaff leaders met with U.S.

Federal officials design the project and cover the majority of its cost, while local authorities handle land acquisition. “It’s something the Corps designs and the Corps pays for the majority of it. The city has done everything that we’ve needed to do- and that includes purchasing land from the BNSF railroad and purchasing private property along where the new channel of the Rio de Flag will flow,” Flagstaff Mayor Becky Daggett told KJZZ.
“I’m very appreciative of our senators and Congressman Crane for recognizing how critical this project is — and appreciative of BNSF and the Army Corps,” Daggett said.
The initiative was originally authorized in 2000 under the Water Resources Development Act, wisevoter.com reported. Rising expenses forced two subsequent re-authorizations as estimated costs climbed to $244 million. “It’s been a complicated project, and its a huge project, but it really has taken more time than I think any of us here in Flagstaff would have liked to have seen,” Daggett said.
As the project has increased in price, that is when the city has had to do extra work to get federal money assigned to address the cost increases, she said.

Under the current financial structure, the city covers 35% of the total cost out of pocket while federal funds from the Army Corps of Engineers pay the remainder, though wisevoter.com said that additional federal backing remains unconfirmed. Flagstaff has already spent $12.5 million on smaller resilience measures, KJZZ reported.
“I know this is a complex project, but I’ll keep emphasizing that we cannot afford one more delay. We have to get started next year, and get this project finished as soon as possible,” Daggett told KJZZ.