Home » today » News » This Thursday concludes the installation of switches to energize lines 1, 2 and 3 of the CDMX Metro: Florencia Serranía

This Thursday concludes the installation of switches to energize lines 1, 2 and 3 of the CDMX Metro: Florencia Serranía

The general director of Metro Collective Transport System, Florence Serrania, reported that in relation to the progress of the actions to restore the service of the Lines 1, 2 and 3, this Thursday the installation of 100% of the switches to energize the said lines is completed, which will allow to restore the electricity supply for the Sunday, January 17.

Likewise, he highlighted that the equipment that will facilitate the control of the switches in the Central Emerging Control Post was completed and with this a 50% advance is achieved.

In the process of rehabilitation of the connection of the transformers to the central energy control post, it has progressed 40%; The same percentage of progress in the operation with safety and control protocols for each line, the assembly of Telemetry modules that will allow the trains to be visualized on the line is in progress.

“The verification of the control and automatic piloting systems for Line 1 is still ongoing. Also, as we reported yesterday, lines 4, 5 and 6 are providing service and we are moving forward to reestablish line 1 on January 25, “he said.

Regarding the operation of lines 4, 5 and 6, he highlighted that the train circulation safety It is guaranteed through the automatic piloting system that has a protection system that prevents the advance of a train beyond the safety distance.

“Communication via Tetra regulator-operator is shielded and secure, and allows knowing the position of the trains in real time,” he stressed.

Also read: Passengers suffer frustration and despair due to lack of Metro on 6 lines